Design, Supply, Testing and Commissioning of Industrial Complex for Solid Radioactive Waste Management (ICSRM)

Contract

Under the G7 Agreement made with Ukrainian government in relation to the Chernobyl NPP decommissioning, NUKEM was awarded a contract funded by the European Union under the TACIS program. The ICSRM was handed over to the customer in 2009. The hot commissioning was completed in 2015.

Description

The project consists of four Lots:

  • Lot 0 – Installation of an interim storage facility for solid low-level waste in the existing building
  • Lot 1 – Installation of a retrieval facility for low, intermediate and high level long-lived waste
  • Lot 2 – Construction of a waste treatment facility for solid and liquid radioactive waste allowing for remote sorting, incineration, compaction, evaporation and cementation.
  • Lot 3 – Construction of a near-surface storage facility for low and intermediate level short-lived waste

Services

NUKEM provided the following services:

  • Process definition, Basic and Detail Design
  • Construction of the waste treatment building
  • Procurement and installation of the process equipment
  • Licensing support
  • Installation and cold commissioning
  • Personnel training
We use cookies

We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies). You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.