Dismantling of 4 Reactor Pressure Vessels at Oskarshamn NPP and Barsebäck NPP

Contract

The Uniper Anlagenservice led consortium with NUKEM has been awarded the contract for the dismantling of in total four reactor pressure vessels, two at Oskarshamn NPP and two at Barsebäck NPP.

Description

The dismantling of the Barsebäck reactor pressure vessels is scheduled to begin in 2020 after approval of the Dismantling Notice by the Swedish Radiation Safety Authority SSM. The overall project schedule foresees one year for the dismantling of each RPV. The entire project is expected to be completed at Oskarshamn in 2024. The segmentation and packaging of the RPV is an important work package in the Client’s overall Nuclear Decommissioning Programme. The dismantling will be performed consecutively, starting in Barsebäck and then moving on to Oskarshamn so as to ensure a “lead and learn” approach.

Services

The following services will be provided by the Consortium: Design and procurement of the segmentation equipment and tools Segmentation planning Waste optimization and preliminary packaging plan Logistics concept Radiation protection planning and radiation protection measures Concept for HSSE and radiation safety RPV segmentation including: Segmentation of the RPV lid Removal of the RPV insulation material Pre- and post-segmentation of the RPV

Questions? We are here for you.

Fast, personal and competent - get in touch with us.

We use cookies

We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies). You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.